Blast Furnace Structural Steel and Duct Installation

Closely coordinated project minimizes production interruptions.

Over the 10 month schedule McGraw/Kokosing furnished and installed 450′ long by 11′ main duct run at an elevation of 70′ between the cast house and baghouse facilities; 180 tons of structural steel supports, platforms, and walkways; 650 linear feet of 8 to 11 foot diameter duct, transitions and hoods in the Cast Houses and under the Skip Hoist; and numerous electrical, structural, and pipe relocations.

All of the work was closely coordinated with plant operations and maintenance crews during operating turns, down turns and through a major outage to ensure project was completed with minimal production interruptions.