Blast Furnace Cast House Extension

Offsite pre-assembly ensured the Cast House Extension project was completed without interruption of plant iron making operations.

The Blast Furnace Cast House Extension project was accomplished by pre-assembling sections of roof, access ramp and even foundation forms complete with rebar and anchor bolts.

The large pre-assembled sections were transported and erected at the project site between iron casts. The foundations were accomplished with excavation, form setting, concrete pours and backfilling being completed during scheduled 8-hour windows to prevent plant production downtime.