Steel

GAN Vessel Installation

Careful planning and execution of Critical Lifts and heavy transport were required to erect 80’ tall GAN vessel.

McGraw/Kokosing was contracted to install a new GAN vessel in an operating steel plant. 

The project began with pipe fabrication at our off-site facility in Monroe. Preparation on site included site excavation, installation of 16 auger cast piles and pouring the 23’ x 30’ pile cap. The GAN Vessel was unloaded at the rail yard and transported over 1-mile to the job site by a self-propelled hydraulic platform trailer.  Once the vessel was set, we completed the installation of the process piping and instrumentation.

Related Projects

Ready to Meet Us?

Contact us today for a quote on your next project.

Contact us